Wernsing Feuerungsanlage
Wernsing Feuerungsanlage is a combustion of fuels installation in Germany. In 2025 it reported 16,567 tonnes of verified emissions against 19,789 free allowances.
Key figures
Country
Activity
Installation ID
DE 1209
Verified emissions, 2025
16,567 tCO₂e
Free allocation, 2025
19,789 allowances
Allowance position, 2025
3,222 surplus
Compliance, 2024
A
Permit
14310-0653
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 16,567 | 19,789 | 3,222 surplus |
| 2024 | 23,683 | 19,789 | 3,894 short |
| 2023 | 43,780 | 18,872 | 24,908 short |
| 2022 | 42,883 | 17,691 | 25,192 short |
| 2021 | 40,702 | 17,059 | 23,643 short |
| 2020 | 39,481 | 14,054 | 25,427 short |
| 2019 | 42,194 | 15,590 | 26,604 short |
| 2018 | 41,923 | 17,175 | 24,748 short |
| 2017 | 41,208 | 18,807 | 22,401 short |
| 2016 | 41,016 | 20,485 | 20,531 short |
| 2015 | 36,586 | 22,208 | 14,378 short |
| 2014 | 36,009 | 23,978 | 12,031 short |
| 2013 | 35,365 | 23,740 | 11,625 short |
Verified emissions changed by -53.2% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
Free allocation exceeded verified emissions in 2025, by 3,222 allowances.
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Germany, largest first.
- Kraftwerk Neurath 12,074,600 t in 2025
- Kraftwerk Niederaußem 11,356,402 t in 2025
- Kraftwerk Jänschwalde 9,631,288 t in 2025
- Kraftwerk Schwarze Pumpe 8,715,923 t in 2025
- Kraftwerk Weisweiler 8,312,179 t in 2025
Questions about Wernsing Feuerungsanlage
How much did Wernsing Feuerungsanlage emit in 2025?
16,567 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Wernsing Feuerungsanlage receive?
19,789 in 2025.
Did Wernsing Feuerungsanlage surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.