Data Processing Centre - DUB 8
Data Processing Centre - DUB 8 is a combustion of fuels installation in Ireland. In 2025 it reported 49 tonnes of verified emissions against 0 free allowances.
Key figures
Country
Activity
Installation ID
IE 206852
Verified emissions, 2025
49 tCO₂e
Free allocation, 2025
None
Allowance position, 2025
49 short
Compliance, 2024
A
Permit
IE-GHG171
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 49 | none | 49 short |
| 2024 | 206 | none | 206 short |
| 2023 | 165 | none | 165 short |
| 2022 | 309 | none | 309 short |
| 2021 | 215 | none | 215 short |
| 2020 | 622 | none | 622 short |
| 2019 | 413 | none | 413 short |
| 2018 | 343 | none | 343 short |
| 2017 | 379 | none | 379 short |
| 2016 | 337 | none | 337 short |
| 2015 | 240 | none | 240 short |
| 2014 | 208 | none | 208 short |
| 2013 | 111 | none | 111 short |
Verified emissions changed by -55.9% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 49 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €4,209. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Ireland, largest first.
- Aughinish Alumina 1,107,056 t in 2025
- Dublin Bay Power Plant 886,437 t in 2025
- Whitegate Power Station 800,308 t in 2025
- Aghada CCGT 748,142 t in 2025
- ESB Poolbeg Generating Station 742,480 t in 2025
Questions about Data Processing Centre - DUB 8
How much did Data Processing Centre - DUB 8 emit in 2025?
49 tonnes of verified emissions, per EU Union Registry compliance data.
Did Data Processing Centre - DUB 8 surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.