Google Ireland Data Center

Google Ireland Data Center is a combustion of fuels installation in Ireland. In 2025 it reported 213 tonnes of verified emissions against 0 free allowances.

Key figures

Country

Ireland

Activity

Combustion of fuels

Installation ID

IE 205782

Verified emissions, 2025

213 tCO₂e

Free allocation, 2025

None

Allowance position, 2025

213 short

Compliance, 2024

A

Permit

IE-GHG170

Data as of

1 April 2026

Emissions and free allocation by year

Verified emissions Free allocation
Verified emissions and free allocation of Google Ireland Data CenterVerified emissions and free allocation from 2013 to 2025.01252503755002013 verified emissions: 10 t2014 verified emissions: 82 t2015 verified emissions: 310 t2016 verified emissions: 87 t2017 verified emissions: 31 t2018 verified emissions: 164 t2019 verified emissions: 321 t2020 verified emissions: 66 t2021 verified emissions: 152 t2022 verified emissions: 172 t2023 verified emissions: 50 t2024 verified emissions: 50 t2025 verified emissions: 213 t2013201520172019202120232025
YearVerified emissions (t) Free allocationPosition
2025 213 none 213 short
2024 50 none 50 short
2023 50 none 50 short
2022 172 none 172 short
2021 152 none 152 short
2020 66 none 66 short
2019 321 none 321 short
2018 164 none 164 short
2017 31 none 31 short
2016 87 none 87 short
2015 310 none 310 short
2014 82 none 82 short
2013 10 none 10 short

Verified emissions changed by +2,030% from 2013 to 2025.

Source: European Commission, Union Registry · Data as of 1 April 2026

Allowance position

In 2025, verified emissions exceeded free allocation by 213 allowances, which the operator had to obtain.

Illustrative value at the latest reference price of €85.90 (28 September 2026): €18,297. Not the installation's actual cost, which depends on when and how it acquired allowances.

Price source: EU ETS primary auctions · latest price

Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.

Nearby installations

Combustion of fuels installations in Ireland, largest first.

Questions about Google Ireland Data Center

How much did Google Ireland Data Center emit in 2025?

213 tonnes of verified emissions, per EU Union Registry compliance data.

Did Google Ireland Data Center surrender enough allowances?

Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.