Intel Ireland
Intel Ireland is a combustion of fuels installation in Ireland. In 2025 it reported 57,998 tonnes of verified emissions against 5,515 free allowances.
Key figures
Country
Activity
Installation ID
IE 45
Verified emissions, 2025
57,998 tCO₂e
Free allocation, 2025
5,515 allowances
Allowance position, 2025
52,483 short
Compliance, 2024
A
Permit
IE-GHG058
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 57,998 | 5,515 | 52,483 short |
| 2024 | 54,847 | 5,515 | 49,332 short |
| 2023 | 51,274 | 5,515 | 45,759 short |
| 2022 | 54,168 | 6,680 | 47,488 short |
| 2021 | 43,205 | 6,680 | 36,525 short |
| 2020 | 44,067 | 25,407 | 18,660 short |
| 2019 | 46,384 | 25,942 | 20,442 short |
| 2018 | 43,367 | 26,476 | 16,891 short |
| 2017 | 42,433 | 27,002 | 15,431 short |
| 2016 | 40,063 | 27,524 | 12,539 short |
| 2015 | 37,252 | 28,039 | 9,213 short |
| 2014 | 29,070 | 28,550 | 520 short |
| 2013 | 28,429 | 29,055 | 626 surplus |
Verified emissions changed by +104% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 52,483 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €4,508,290. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Ireland, largest first.
- Aughinish Alumina 1,107,056 t in 2025
- Dublin Bay Power Plant 886,437 t in 2025
- Whitegate Power Station 800,308 t in 2025
- Aghada CCGT 748,142 t in 2025
- ESB Poolbeg Generating Station 742,480 t in 2025
Questions about Intel Ireland
How much did Intel Ireland emit in 2025?
57,998 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Intel Ireland receive?
5,515 in 2025.
Did Intel Ireland surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.