Microsoft Dublin Data Centre Campus
Microsoft Dublin Data Centre Campus is a combustion of fuels installation in Ireland. In 2025 it reported 1,332 tonnes of verified emissions against 0 free allowances.
Key figures
Country
Activity
Installation ID
IE 208162
Verified emissions, 2025
1,332 tCO₂e
Free allocation, 2025
None
Allowance position, 2025
1,332 short
Compliance, 2024
A
Permit
IE-GHG179
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 1,332 | none | 1,332 short |
| 2024 | 852 | none | 852 short |
| 2023 | 722 | none | 722 short |
| 2022 | 1,028 | none | 1,028 short |
| 2021 | 1,062 | none | 1,062 short |
| 2020 | 604 | none | 604 short |
| 2019 | 558 | none | 558 short |
| 2018 | 140 | none | 140 short |
| 2017 | 175 | none | 175 short |
| 2016 | 292 | none | 292 short |
| 2015 | 640 | none | 640 short |
| 2014 | 460 | none | 460 short |
| 2013 | 292 | none | 292 short |
Verified emissions changed by +356.2% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 1,332 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.90 (28 September 2026): €114,419. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Ireland, largest first.
- Aughinish Alumina 1,107,056 t in 2025
- Dublin Bay Power Plant 886,437 t in 2025
- Whitegate Power Station 800,308 t in 2025
- Aghada CCGT 748,142 t in 2025
- ESB Poolbeg Generating Station 742,480 t in 2025
Questions about Microsoft Dublin Data Centre Campus
How much did Microsoft Dublin Data Centre Campus emit in 2025?
1,332 tonnes of verified emissions, per EU Union Registry compliance data.
Did Microsoft Dublin Data Centre Campus surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.