Mondelez Ireland Production Limited - Rathmore
Mondelez Ireland Production Limited - Rathmore is a combustion of fuels installation in Ireland. It last reported verified emissions for 2020: 5,978 tonnes.
The Union Registry records this account as closed (13-JUL-21).
Key figures
Country
Activity
Installation ID
IE 77
Verified emissions, 2020
5,978 tCO₂e
Free allocation, 2020
1,059 allowances
Allowance position, 2020
Not available
Compliance
Not published
Permit
IE-GHG098
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2020 | 5,978 | 1,059 | 4,919 short |
| 2019 | 5,633 | 1,338 | 4,295 short |
| 2018 | 5,916 | 1,629 | 4,287 short |
| 2017 | 5,947 | 3,857 | 2,090 short |
| 2016 | 7,521 | 4,477 | 3,044 short |
| 2015 | 8,815 | 5,117 | 3,698 short |
| 2014 | 8,170 | 5,777 | 2,393 short |
| 2013 | 9,419 | 6,455 | 2,964 short |
Verified emissions changed by -36.5% from 2013 to 2020.
Source: European Commission, Union Registry ยท Data as of 1 April 2026
Allowance position
No verified emissions were reported for 2025, so there is no position for the latest year.
Nearby installations
Combustion of fuels installations in Ireland, largest first.
- Aughinish Alumina 1,107,056 t in 2025
- Dublin Bay Power Plant 886,437 t in 2025
- Whitegate Power Station 800,308 t in 2025
- Aghada CCGT 748,142 t in 2025
- ESB Poolbeg Generating Station 742,480 t in 2025
Questions about Mondelez Ireland Production Limited - Rathmore
How much did Mondelez Ireland Production Limited - Rathmore emit in 2020?
5,978 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Mondelez Ireland Production Limited - Rathmore receive?
1,059 in 2020.