The Pfizer Biotech Campus at Grange Castle
The Pfizer Biotech Campus at Grange Castle is a combustion of fuels installation in Ireland. In 2025 it reported 29,494 tonnes of verified emissions against 4,549 free allowances.
Key figures
Country
Activity
Installation ID
IE 24
Verified emissions, 2025
29,494 tCO₂e
Free allocation, 2025
4,549 allowances
Allowance position, 2025
24,945 short
Compliance, 2024
A
Permit
IE-GHG026
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | 29,494 | 4,549 | 24,945 short |
| 2024 | 33,573 | 4,549 | 29,024 short |
| 2023 | 32,849 | 4,549 | 28,300 short |
| 2022 | 32,339 | 4,549 | 27,790 short |
| 2021 | 31,492 | 4,549 | 26,943 short |
| 2020 | 32,235 | 15,489 | 16,746 short |
| 2019 | 31,765 | 15,815 | 15,950 short |
| 2018 | 32,694 | 16,140 | 16,554 short |
| 2017 | 33,243 | 16,461 | 16,782 short |
| 2016 | 33,083 | 16,779 | 16,304 short |
| 2015 | 33,606 | 17,094 | 16,512 short |
| 2014 | 33,191 | 17,405 | 15,786 short |
| 2013 | 34,391 | 17,713 | 16,678 short |
Verified emissions changed by -14.2% from 2013 to 2025.
Source: European Commission, Union Registry · Data as of 1 April 2026
Allowance position
In 2025, verified emissions exceeded free allocation by 24,945 allowances, which the operator had to obtain.
Illustrative value at the latest reference price of €85.50 (25 September 2026): €2,132,798. Not the installation's actual cost, which depends on when and how it acquired allowances.
Price source: EU ETS primary auctions · latest price
Compliance status for 2024: A. The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Ireland, largest first.
- Aughinish Alumina 1,107,056 t in 2025
- Dublin Bay Power Plant 886,437 t in 2025
- Whitegate Power Station 800,308 t in 2025
- Aghada CCGT 748,142 t in 2025
- ESB Poolbeg Generating Station 742,480 t in 2025
Questions about The Pfizer Biotech Campus at Grange Castle
How much did The Pfizer Biotech Campus at Grange Castle emit in 2025?
29,494 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did The Pfizer Biotech Campus at Grange Castle receive?
4,549 in 2025.
Did The Pfizer Biotech Campus at Grange Castle surrender enough allowances?
Its compliance status for 2024 is recorded as "A": The number of allowances surrendered by 30 September 2025 was greater than or equal to verified emissions.