Wexford Proteins Ltd
Wexford Proteins Ltd is a combustion of fuels installation in Ireland. It last reported verified emissions for 2023: 894 tonnes.
The Union Registry records this account as closed (23-APR-24).
Key figures
Country
Activity
Installation ID
IE 109
Verified emissions, 2023
894 tCO₂e
Free allocation, 2023
559 allowances
Allowance position, 2023
Not available
Compliance, 2023
A
Permit
IE-GHG148
Data as of
1 April 2026
Emissions and free allocation by year
| Year | Verified emissions (t) | Free allocation | Position |
|---|---|---|---|
| 2025 | none | 0 | |
| 2024 | none | 0 | |
| 2023 | 894 | 559 | 335 short |
| 2022 | 1,423 | 559 | 864 short |
| 2021 | 1,325 | 559 | 766 short |
| 2020 | 1,503 | 734 | 769 short |
| 2019 | 1,282 | 1,406 | 124 surplus |
| 2018 | 1,618 | 2,744 | 1,126 surplus |
| 2017 | 2,955 | 2,829 | 126 short |
| 2016 | 3,007 | 2,914 | 93 short |
| 2015 | 2,621 | 3,001 | 380 surplus |
| 2014 | 2,711 | 3,089 | 378 surplus |
| 2013 | 2,831 | 3,175 | 344 surplus |
Verified emissions changed by -68.4% from 2013 to 2023.
Source: European Commission, Union Registry ยท Data as of 1 April 2026
Allowance position
No verified emissions were reported for 2025, so there is no position for the latest year.
Compliance status for 2023: A. The number of allowances surrendered by 30 September 2024 was greater than or equal to verified emissions.
Nearby installations
Combustion of fuels installations in Ireland, largest first.
- Aughinish Alumina 1,107,056 t in 2025
- Dublin Bay Power Plant 886,437 t in 2025
- Whitegate Power Station 800,308 t in 2025
- Aghada CCGT 748,142 t in 2025
- ESB Poolbeg Generating Station 742,480 t in 2025
Questions about Wexford Proteins Ltd
How much did Wexford Proteins Ltd emit in 2023?
894 tonnes of verified emissions, per EU Union Registry compliance data.
How many free allowances did Wexford Proteins Ltd receive?
559 in 2023.
Did Wexford Proteins Ltd surrender enough allowances?
Its compliance status for 2023 is recorded as "A": The number of allowances surrendered by 30 September 2024 was greater than or equal to verified emissions.