Jilin Liaoyuan Meihe Coal Mine Methane Power Generation Project

Registry Record

Registry

Verra

Project ID

VCS116

Country

China

Category

GHG Management

Methodology

acm0008

Status

Not stated

Credits Issued

81,200 tCO₂e

Credits Retired

79,815 tCO₂e

Data as of

1 June 2026

Issuance and retirement by vintage

Issued Retired
Issuance and retirement by vintageVintages 2006 to 2008: 81,200 tonnes issued and 79,815 retired.025k50k75k100k2006 issued: 14,489 tonnes2006 retired: 13,744 tonnes20062007 issued: 50,143 tonnes2007 retired: 50,143 tonnes20072008 issued: 16,568 tonnes2008 retired: 15,928 tonnes2008
VintageIssued (tCO₂e)Retired (tCO₂e)
200816,56815,928
200750,14350,143
200614,48913,744

Source: Registry records · Data as of 1 June 2026

Credit Passport in detail

ICVCM quality status

ICVCM approved some versions of this methodology and not others. The version this project uses is not in registry data.

  • Programme: Verified Carbon Standard, CCP-eligible since May 2024.
  • ACM0008 - Abatement of methane from coal mines - 6.0-8.0: approved
  • ACM0008 - Abatement of methane from coal mines - 8.0: under assessment

The CCP label is applied to credits by the registry, issuance by issuance. An approved methodology means credits from this project can be eligible; it does not mean every credit carries the label.

Source: ICVCM assessment decisions · Decisions read 19 September 2026

What this layer checks

CORSIA screen

A screen against published ICAO criteria, not an eligibility determination.

First phase, 2024 to 2026

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2024 to 2026.
  • DatesDoes not passCredits were issued for vintage 2006, so crediting began before 1 January 2016.
  • Host country authorisationCannot be confirmed from available dataAuthorisation is granted per activity. This screen cannot confirm whether this project holds a Letter of Authorization.

Second phase, 2027 to 2029

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2027 to 2029.
  • DatesDoes not passCredits were issued for vintage 2006, so crediting began before 1 January 2016.

Programme-specific exclusions were not assessed. Host country context is under Article 6 below.

Source: ICAO eligibility decisions and registry records · Criteria verified 25 September 2026

What this layer checks

China and Article 6

Bilateral agreements
0
Authority for the Paris Agreement Crediting Mechanism
Appointed
Participation requirements for the Mechanism
Not published
Cooperative approaches
0
Article 6.2 activities
0
Crediting Mechanism activities approved by the host
0
Crediting Mechanism activities registered
0

This is country-level context. It does not show whether this project is authorised.

Source: UN Article 6 tracking · Data as of 4 September 2026

What this layer checks

Recorded buyers

No organisation named as beneficiary in registry records.

Retired credits from this project? See what a company can still say about them under the EU green claims rules.

Source: Registry records · Data as of 1 June 2026

What this layer checks

Jilin Liaoyuan Meihe Coal Mine Methane Power Generation Project is registered with Verra under the acm0008 protocol, located in China. As of 1 June 2026, registry records show 81,200 tonnes issued and 79,815 tonnes retired. This reflects registry-reported figures, not an independent quality assessment.

Related

Similar projects

Same methodology and country, largest issuance first.

Questions about this project

How many credits has Jilin Liaoyuan Meihe Coal Mine Methane Power Generation Project issued?

81,200 tonnes of credits have been issued and 79,815 retired, according to registry records as of 1 June 2026.

What is the ICVCM status of this project's methodology?

ICVCM approved some versions of this methodology and not others. The version this project uses is not in registry data. The CCP label is applied to credits by the registry, issuance by issuance.

Registry data as of June 1, 2026