210 MW Musi Hydro Power Plant, Bengkulu

Registry Record

Registry

Verra

Project ID

VCS487

Country

Indonesia

Category

Renewable Energy

Methodology

acm0002

Status

Registered

Credits Issued

7,635,581 tCO₂e

Credits Retired

5,850,891 tCO₂e

Data as of

1 June 2026

Issuance and retirement by vintage

Issued Retired
Issuance and retirement by vintageVintages 2009 to 2020: 7,635,581 tonnes issued and 5,850,891 retired.0250k500k750k1M2009 issued: 421,938 tonnes2009 retired: 320,762 tonnes20092010 issued: 691,297 tonnes2010 retired: 294,441 tonnes20102011 issued: 517,927 tonnes2011 retired: 69,858 tonnes20112012 issued: 534,274 tonnes2012 retired: 526,195 tonnes20122013 issued: 578,211 tonnes2013 retired: 576,836 tonnes20132014 issued: 516,299 tonnes2014 retired: 514,983 tonnes20142015 issued: 477,279 tonnes2015 retired: 71,155 tonnes20152016 issued: 639,358 tonnes2016 retired: 608,066 tonnes20162017 issued: 784,303 tonnes2017 retired: 609,780 tonnes20172018 issued: 803,211 tonnes2018 retired: 675,056 tonnes20182019 issued: 712,808 tonnes2019 retired: 674,345 tonnes20192020 issued: 958,676 tonnes2020 retired: 909,414 tonnes2020
VintageIssued (tCO₂e)Retired (tCO₂e)
2020958,676909,414
2019712,808674,345
2018803,211675,056
2017784,303609,780
2016639,358608,066
2015477,27971,155
2014516,299514,983
2013578,211576,836
2012534,274526,195
2011517,92769,858
2010691,297294,441
2009421,938320,762

Source: Registry records · Data as of 1 June 2026

Credit Passport in detail

ICVCM quality status

Methodology assessed by ICVCM and not approved.

  • Programme: Verified Carbon Standard, CCP-eligible since May 2024.
  • ACM0002 - Grid-connected electricity generation from renewable sources - 1.0-21.0: does not meet the Core Carbon Principles

The CCP label is applied to credits by the registry, issuance by issuance. An approved methodology means credits from this project can be eligible; it does not mean every credit carries the label.

Source: ICVCM assessment decisions · Decisions read 19 September 2026

What this layer checks

CORSIA screen

A screen against published ICAO criteria, not an eligibility determination.

First phase, 2024 to 2026

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2024 to 2026.
  • DatesDoes not passCredits were issued for vintage 2009, so crediting began before 1 January 2016.
  • Host country authorisationCannot be confirmed from available dataAuthorisation is granted per activity. This screen cannot confirm whether this project holds a Letter of Authorization.

Second phase, 2027 to 2029

  • ProgrammePassesVerified Carbon Standard is approved by ICAO for 2027 to 2029.
  • DatesDoes not passCredits were issued for vintage 2009, so crediting began before 1 January 2016.

Programme-specific exclusions were not assessed. Host country context is under Article 6 below.

Source: ICAO eligibility decisions and registry records · Criteria verified 25 September 2026

What this layer checks

Indonesia and Article 6

Bilateral agreements
4
Authority for the Paris Agreement Crediting Mechanism
Appointed
Participation requirements for the Mechanism
Published
Cooperative approaches
1
Article 6.2 activities
40
Crediting Mechanism activities approved by the host
14
Crediting Mechanism activities registered
0

This is country-level context. It does not show whether this project is authorised.

Source: UN Article 6 tracking · Data as of 4 September 2026

What this layer checks

Recorded buyers

Organisations named in registry retirement records. Many retirements name no beneficiary, so this list is partial.

17.1% of retired tonnes name an organisation as beneficiary.

OrganisationTonnes retiredLatest year
Toho Gas411,2722022
Toucan139,9772021
Lhoist130,0002024
Zukunftswerk121,2192025
Estra Energie50,0002025
Booking Holdings50,0002022
Minter Ellison40,7472024
Österreichische Post30,0002015
The University of Melbourne25,0002021

Retired credits from this project? See what a company can still say about them under the EU green claims rules.

Source: Registry records · Data as of 1 June 2026

What this layer checks

210 MW Musi Hydro Power Plant, Bengkulu is registered with Verra under the acm0002 protocol, located in Indonesia. As of 1 June 2026, registry records show 7,635,581 tonnes issued and 5,850,891 tonnes retired. This reflects registry-reported figures, not an independent quality assessment.

Related

Similar projects

Same methodology and country, largest issuance first.

Questions about this project

How many credits has 210 MW Musi Hydro Power Plant, Bengkulu issued?

7,635,581 tonnes of credits have been issued and 5,850,891 retired, according to registry records as of 1 June 2026.

What is the ICVCM status of this project's methodology?

Methodology assessed by ICVCM and not approved. The CCP label is applied to credits by the registry, issuance by issuance.

Which organisations have retired credits from 210 MW Musi Hydro Power Plant, Bengkulu?

Registry records name 9 organisations, including Toho Gas, Toucan, Lhoist. Many retirements name no beneficiary.

Registry data as of June 1, 2026