EU ETS installations in Ireland
In 2025, 117 installations reported 10,670,686 tonnes of verified emissions and received 3,619,072 free allowances. 142 installations are on record since 2013.
Reporting in 2025
117
Verified emissions
10,670,686 t
Free allocation
3,619,072
Allocation as share of emissions
33.9%
Source: European Commission, Union Registry · Data as of 1 April 2026
By activity, 2025
- Combustion of fuels 8,022,821 t · 106
- Production of cement clinker 2,199,312 t · 4
- Refining of mineral oil 291,879 t · 1
- Production of lime, or calcination of dolomite/magnesite 118,905 t · 3
- Production or processing of gypsum or plasterboard 34,045 t · 1
- Manufacture of ceramics 3,638 t · 1
- Capture of greenhouse gases under Directive 2009/31/EC 86 t · 1
Installations
Largest 2025 verified emissions first; installations that did not report in 2025 follow.
- Sterling Pharma Ringaskiddy Limited 3,740 t in 2025
- Kingscourt Brick 3,638 t in 2025
- WuXi Vaccines Ireland Limited 3,498 t in 2025
- Lakeland Dairies Drying Plant 3,388 t in 2025
- Masonite Ireland 3,009 t in 2025
- ESB - North Wall TEGP 2,841 t in 2025
- MSD Ireland (Dunboyne Biologics) 2,796 t in 2025
- Eli Lilly and Company 2,469 t in 2025
- Zoetis Belgium (Irish Branch) SA 2,274 t in 2025
- Hovione Limited 2,094 t in 2025
- Smartply Europe 1,938 t in 2025
- Microsoft Dublin Data Centre Campus 1,332 t in 2025
- Edenderry Power Plant 958 t in 2025
- DUB54 Data Processing Centre 452 t in 2025
- DUB 56 Data Processing Centre 368 t in 2025
- Equinix Hyperscale 1 (DB5) Limited 364 t in 2025
- Google Ireland Data Center 213 t in 2025
- Waspar Limited 193 t in 2025
- DUB14 Profile Park 157 t in 2025
- EDCDUB Campus 122 t in 2025
- Data Processing Centre - DUB 58 120 t in 2025
- ESSDUB97 86 t in 2025
- ADSIL DUB 10, Data Processing Centre 80 t in 2025
- DUB9 79 t in 2025
- KDCR DUB1 78 t in 2025